Featured articles

  • Optimization of Hydro-Power Plants for Generation-part 4
  • Optimization of Hydro-Power Plants for Generation-part 3
  • Optimization of Hydro Power Plants for Generation-part 2
  • Optimization of Hydro-Power Plants for Generation-part 1

Operation and maintenance of hydropower stations planning and management – an Indian perspective-Part 5

Posted on August 18th, 2012 by admin  |  No Comments »

5 Preventive maintenance of Hydro Generators

Preventive maintenance ensures a long trouble free operation of the generator. Given in the following Table are the recommended daily, monthly, once in 3 months, half yearly & yearly maintenance checks to be conducted on the generator. While it is appreciated that it is not always possible to rigidly follow this schedule due to generator loading constraints, the recommendation given may be taken as a guide line and these may be altered slightly, based on his experience.

After the first 600 hours operation of the unit, the checks having periodicity of half yearly and yearly in the following schedule should be carried out.

 

Sl.No. Description Periodicity Remarks
1.00 Stator:
1.01 Temperature record on log sheet for core and winding, hot and cold air temperature Hourly
1.02 Visual inspection of the overhang parts of the stator winding. Once in 3 months
1.03 Checking the fixing of winding,condition of winding joints withbus bars etc. Once in 3 months
1.04 Clean the winding with dry &clean compressed air (2 to 3 kg/cm2). Once in 3 months Cleaning to be done such that the dust does not collect in sidemachine
1.05 Check overhang parts of statorwinding, bus bars, inner periphery of stator core (if possible), parts ofstator winding in slots (specially at sector joint) binding & spacers between the winding bars/bandage rings. Yearly
1.06 Check looseness of overhang, busbars, slot wedges etc. Yearly
1.07 Check the fixing of stator active iron with the frame body in all possible places. If it is necessary,tighten the studs of pressing plates. Yearly
1.08 Check pins & fixing of stator with foundations. Yearly
1.09 Check D.C. resistance, IR & PI value. Yearly Record to be maintained
1.10 Check functioning of RTDs of stator. Yearly -do-
1.11 Blow the winding, active iron and bandage rings etc. with dry &clean compressed air (2 to 3kg/cm2). Yearly
1.12 After cleaning apply Red-gel coat on the overhang. Yearly Not required during 600hours inspection.
1.13 In case of excessive wetting ofstator winding during conditions such as flooding, drying ofwinding by passing current is not

allowed initially as hydrolysis of

water may take place. This is

harmful to the winding.

As per requirement External heating arrangement is to be provided till wetness isremoved.
2.00 ROTOR:
2.01 Check rotor winding and insulation details of current carrying leads. Once in 3 months
2.02 Check the condition of inter polar connections Once in 3 months
2.03 Check the condition of damper winding. Once in 3 months
2.04 Check the locking of pole wedges.If required carryout additional wedging. Yearly
2.05 Check locking of rim wedges. Yearly In case the wedges areloose contactmanufacturer beforeattempting any

rectification.

2.06 Check the gaps of spider arms,brake track. Yearly
2.07 Check tightening & proper lockingof all fasteners. Yearly
2.08 Clean rotor from dust by blowingcompressed air free from moisture(2 to 3 kg/ cm2). Yearly
2.09 Measure D.C. resistance and IRvalue of rotor winding. Yearly Keep a record
2.10 Check the pole coils for inter turn fault. Yearly Not required during 600hours inspection.
3.00 Slip ring and Brush Rocker
3.01 Check sparking Every shift
3.02 Check pitting & Grooving of slip ring Monthly In case of excessivegrooving rectify bygrinding.
3.03 Check IR value of rotor throughslip rings before & after cleaningslip rings. Once in 3 months Keep record
3.04 Clean the brush rocker, Brushes,slip rings and the surroundingareas. Monthly Special care must betaken to clear carbondust from ‘V’ shapedinsulation pieces fitted

between slip rings.

3.05 Check brush wear & springtension Monthly Use a precision springbalance for adjustingspring tension. Thecarbon brushes can be

used till it is not possible

to measure/ adjust spring

tension.

3.06 Check for absence of oil or oilvapour slip ring area. Every shift. Oil leakages, if any, tobe removed
3.07 Check distance of brush holderfrom slip ring and keep it asspecified in the drawing. Monthly
3.08 New brushes to be used after bedding the brushes. The brushshould not be too tight/ looseinside the holder. While replacing
3.09 Ensure use of same &recommended grade of carbonbrushes on one machine.
3.10 Check all fasteners of slip rings,brush rocker & current carryinglead. Once in 3 months
3.11 Check carbon brushes for absenceof splits, cracks and severe wear. Monthly In case the damage isexcessive, replacecomplete set.
3.12 Inter change polarity of slip rings. Half yearly Not required during 600hrs. inspection
3.13 Carryout thorough cleaning of slipring area. Stop oil leakages in thisarea. Half yearly
3.14 In case the original insulatingenamel unit is peeling off removethe balance payment and applyfree enamel IE –82 dry Yearly While cleaning avoidusing insulating paintremovers.
3.15 Check wobbling at slip rings. At the time ofinstallation/ duringmajor overhauling
4.00 Thrust Bearing
4.01 Measurement of temperatures ofT.B. Pad & Oil by RTD & TSDand record on log sheet. Hourly
4.02 Check & record reading of oillevel relay. Once in a shift.
4.03 Analysis of oil from oil bath. Half yearly Record to be kept.
4.04 Change of oil in T.B. oil bath When centrifugingdoesn’t help inimproving its quality upto acceptable values.
4.05 Check level of oil from the gaugeglass. Any increase in level maybe due to leakage of water in theoil bath from coolers. Once in every shift. Unit should be stoppedin case of leakage fromcooling tube. Pluggingof cooling tubes up to

10% can be done

depending upon bearing

temperature.

4.06 Measures insulation resistance ofT.B. disc. Yearly Not required during 600hours inspection.
4.07 Check calibration of the TSD’s &RTD’s of thrust bearing. Yearly Not required during 600hours inspection.
4.08 Check the working surface ofthrust bearing pads, scrapping, ifrequired, should be carried out with respect to T.B. disc afterapply lard (animal fat) on the pads

& giving rotation to the unit. Load

sharing on T.B. pads and the

verticality of the unit is to be

checked thereafter.

Yearly Not required during 600hrs. inspection
4.09 Check the condition of mirrorsurface of T.B. Disc. Polishing ofthe surface can be done to removeminor scratches. During capitalmaintenance This will require partialdismantling of unit.
4.10 Clean all inner surfaces of oil bathfrom dust, wash them withKerosene and dry with clean cloth. Once in Two years. Oil bath is to be finallyflushed with freshturbine oil; to bediscarded after use.
4.11 Check the condition of weld seamof oil bath & oil pipe lines forleakages visually. Yearly
4.12 Check the condition of insulationof RTD leads. Yearly
4.13 Check if excessive foaming istaking place in oil through gaugeglass. This is normally due tomixing of water leaking from oil

coolers. If oil level is not rising,

the oil may need changing. Oil

sample to be checked.

As required. Watch carefully for risein water level to confirmleakage and attendaccordingly.
4.14 Check if any insulating segmentover T.B. Disc is displaced. During capitalmaintenance
4.15 Check (in case of problem) theintactness of spherical surface ofthrust bolt As per requirement.
4.16 In case of uneven wear of pad,check that the pad eccentricity iscorrect. As per requirement
4.17 Check for proper seating of padsduring each As required
4.18 Change rubber seals & woolenfelts As required
5.00 GUIDE BEARINGS
5.01 Measurement of temperatures ofG.B. pads, oil by RTD & TSD &record on log sheets Hourly
5.02 Check & note reading of levelrelay Once in every shift
5.03 Analysis of oil from oil bath Once in 3 months Record to be kept.
5.04 Change of oil in T.B. oil bath When centrifugingdoesn’t help inimproving its quality upto acceptable values
5.05 Measures insulation resistance ofG.B. pads. Yearly
5.06 Check calibration of TSD’s &RTDs of G.B. Yearly Not required during 600hrs. inspection
5.07 Prior to removal of pads, measureand record guide bearingclearances. As per requirement To be readjusted ifrequired, duringreinstallation
5.08 Check each pad for:i) Absence of scratch marks.Scrapping to be done withrespect to the journal, if

required

ii) Heavy damage on Babbit

surface of pads – full set must be

replaced with genuine spares. The

spare set to be scrapped with

respect to its respective journal

surface by giving rotation to the

unit.

Yearly Not required during 600hrs. inspection
5.09 Check the centering of the unitvis-à-vis the labyrinth/runnerchamber of turbine. Yearly as perrequirement. Not required during 600hours inspection.
5.10 Check the friction surface of thebearing journal. Clean and polishif necessary. Yearly
5.11 Wash pads & journal with aviationpetrol and then carryout assemblyof the guide bearing. Yearly Not required during 600hrs. inspection
5.12 Check the condition of weldingseams of oil bath & leakages fromthem and oil pipe liens. Yearly
5.13 Clean all inner surfaces of oil bathfrom dust, wash them withKerosene and dry with clean cloth. Once in tow years Oil bath is to be finallyflushed with freshturbine oil; to bediscarded after use.
5.14 Change rubber seals and woolenfelts As required
5.15 Check operation of the level relayand its calibrations. Yearly
5.16 Check welding of pad supportblock with oil bath. Yearly
5.17 Check looseness of pad and padsupport bolts. Yearly
5.18 Check condition of pad insulation. Yearly
5.19 Check looseness of bolts holding‘Z’ clamps (in wedge typeconstruction of guide bearings. Yearly
6.00 Air/Oil Coolers
6.01 Check water boxes for clogging by opening them. In case of cloggingclean tubes water boxes with wire/nylon brush. Remove all dirt etc &finally clean with fresh water &

dry.

Yearly This checking may be done frequently ifclogging is more.
6.02 Check the gasket between oilcooler & oil bath & between aircooler & stator frame. Gaskets tobe replaced if required. Yearly Not required during 600hrs. inspection
6.03 When the shutdown exceeds 10days, water from coolers is to bedrained and the coolers kept dry. As required
6.04 Coolers are to be immediatelyattended to as given above at 6.03 On flooding of the unit. This is to safe guardfailure on subsequentcommissioning of theunit.
6.05 Normally up to 10% of the coolingtubes of coolers can be plugged, ifrequired. As required Temperature of thebearing pads/ statorwinding to be taken inview while plugging

tubes of the coolers.

7.00 UPPER DRACKET/ LOWERBRACKET
7.01 External inspection & tighteningof the lock nuts in the radial jacks,if required. Once in 3 months
7.02 Check fixing of the generatorcover plate Once in 3 months
7.03 Check all fasteners of Upper andlower air baffles. Once in 3 months
7.04 Check the value of air gapbetween air baffles and rotor. Yearly Theses gaps are to becompared with originalvalues during erectionand maintained as such,

if required.

7.05 Clean the brackets of dirt & dust. Yearly Cleaning can be donemore often if possible.
7.06 Check fastening between upperbracket & stator and stator andfoundation plates. Yearly
7.07 Check foundation bolts tighteningfor stator & lower bracket. Yearly
7.08 Check all fasteners for locking/tightness Yearly
8.00 Brake pipe line
8.01 Record air pressure available atbrake panel. Every shift Record on log sheet
8.02 Check thickness of brake pad As required Record to be maintainedalong with number of braking in the periodwith Air pressure usedfor braking.
8.03 Measure:i) Time for unit to comebraking speed from rated speedafter signaling the unit to stop. During first spinning/yearly Record by kept. In caseif this time has increasedabnormal then look forincreased guide vanes

clearances. Presence of

oil on brake track or

reduction in air pressure,

defective gauge etc.

8.04 Check if excessive brake dust isgenerated and find its cause. Yearly Clean the affected areasperiodically as required
8.05 During jacking operation lifting ofthe rotor is to be limited to thespecified value (7.0 mm) During jacking Limit switch to besuitably mounted tocheck the rotor lift.
8.06 Keep the unit on jacks which aremechanically locked during eachshut-down of the unit As required
8.07 After each jacking operationensure cleaning of pipe with airunder pressure as provided in thesystem. As required
8.08 Check no oil leaks from return lineduring jacking operation As required
8.09 Check function of the brakingsystem on manual and automaticand the operation of the limitswitches of brake. Check leakage

through pipelines during braking/

jacking.

Yearly Record must bemaintained. In case ofany problem brake panel& brakes are to be

checked & rectified as

required.

8.10 Check all fasteners of brakes andbrake pipe lines & gasketswherever provided. Yearly Not required during 600hours inspection.
8.11 Check the condition of brake trackand its holding with the rotor Yearly Not required during 600hrs. inspection
8.12 Open brake cum jack assembly.Clean the inner surface of dustwith kerosene & reassemble. Yearly Replace the gas ifrequired. Not requiredduring 600 hoursinspection.
9.00 GENERAL
9.01 External examination of parts ofgenerator which are accessible. Once in each shift
9.02 External inspection of air coolers,oil coolers, pipe lines, sealing &control etc. for leakages. Once in each shift
9.03 Ensure cleanliness of all externalaccessible parts of the generator &wipe with clean & dry cloth. Once in each shift
9.04 Check wobbling of the shaft atturbine generator flange/ TGB Daily
9.05 Blow with compressed air theinternal surface of the generator Monthly
9.06 External inspection of currentcarrying leads PMG, Bus Bars,Terminal Blocks, Panels etc. Monthly To be cleaned ifnecessary
9.07 Check the condition of lightinginside the barrel Monthly
9.08 Check the recordings of lightinginside original results. Daily Reasons for variance tobe investigated
9.09 Check for proper cleaning of sliprings. As per requirements
9.10 Check the vibrations at TGB,UGB & LBG predeterminedpoints. Yearly
9.11 Check connections of currentcarrying leads & cables. Tightenthe bolts, if required, afterremoving the insulation. Yearly
9.12 Check the calibration of Electricalmeasuring instruments i.e.voltmeter, ammeter, Active/Reactive Power meter. Frequency

meter, P.F. meter for Stator output,

Voltmeter & Ammeter in Field

winding circuit, energy meter etc.

Yearly
9.13 Check the Sensitivity & Stabilityof Generator Electrical Protectionscheme. As specified by itssupplier.
9.14 Check the working of FireExtinguishing (CO2) systemwithout actually releasing the CO2gas on manual and on auto

operation as per the instructions

provided in O&M manual of the

Fire Extinguishing System

provided by its supplier

Yearly
9.15 Check the characteristics of StaticExcitation system in both auto &manual mode and sensitivity ofvarious limits. As specified in its O&Mmanual.
10.00 OIL PIPE LINE/ EXTERNALOIL COOLING SYSTEM (ifapplicable)
10.01 Check oil pressure at the pumpacross the filter & point of entry tothe bearing. Every shift Record is to bemaintained.
10.02 Check the operation of the electrical contact pressure gauge. Monthly
10.03 Check temperature of bearings ofthe Pump-motor set. Daily This temperature is notto exceed the specifiedlimits. If the temperatureis excessive, check if

lubricating grease is

filled as required.

10.04 Check conditions of gland packingof the pump and see that air is notbeing sucked from here into thesystem. Monthly These are holes in pipeswhich feed oil inbetween the pads.
10.05 Completely clean the oil tank &T.B. oil bath Yearly Not required during 600hours inspection.
10.06 Clean the oil pipe line afterdisconnecting it Yearly Not required during 600hours inspection.
10.07 Check the operation of the valvesof the pipe line. Yearly Not required during 600hours inspection.
10.08 Check the Operation of D.C. pumpmotor set (if provided) Monthly
10.09 Remove sludge from oil tank. Monthly
10.10 Check the temperature of cold &hot oil. Hourly Keep record in the logsheet
10.11 Check the air ventilation cocks ofthe oil tank are open during.Operation of the unit. During start of the unit/during each shift.
10.12 Check pipe line for leakage of oil. Once in each shift
10.13 Check oil sample for acidity,viscosity, moisture content,foreign material & sludge.Formations. Once in 3 months Separate oil sample fromeach bearing should besent for chemicalanalysis & record to be

kept.

10.14 Clean holes for oil entry into theT.B. housing Yearly Not required during 600hrs. inspection

1 – Operation and maintenance of hydropower stations planning and management – an Indian perspective-Part 4

Posted on April 23rd, 2012 by admin  |  No Comments »

4.2 Turbine Guide Bearings

 A number of turbine guide bearing designs are in use. These may be classified as follows:

i) Plain water cooled bearing

ii) Bath type with circular cooling turbines

iii) Bath type with cooling water tubes embedded in the pads.

iv) Rotating bath type.

v) Grease lubrication bearing.

In the case of plain water cooled bearings, either ferrobestos or rubber lined pads are used against a welded shaft sleeve. The ferrobestos lined bearing have given considerable trouble at one of the power station and these had to be replaced by rubber lined pads.

Small diameter cooling pipes embedded in bearing pads have a tendency to clog especially at the time of high silt contents resulting water starvation.

Complaints of excessive oil splashing have been received about the rotating bath type bearing. Grease lubrication bearings have a tendency to clog when in contact with the water and it is very essential to use grease with the right type of properties.

A number of cases of turbine guide bearing failures have come to notice. These are:

i) Starvation of oil in the bath

ii) Failure of cooling water due to clogging of pipe.

iii) Mal-functioning of instruments like RTDs, TSDs, oil level relay and flow relays etc.

To avoid failure of bearing due to cooling water tube, a new design of turbine guide bearing has been developed by BHEL, Hardwar. Two separate oil sumps are located in the top cover in diametrically opposite locations. These sumps, through pipe lines are connected to the oil bath of the bearing. The oil is circulated between sumps and the bath. Top cover being stationed just above the draft tube, separate to cooling water arrangement for bearing oil is not required. The bearing temperatures with this arrangement never go beyond 40oC to 42oC and this design is effectively working at Chila Power Station.

 4.3 Gland Seals

Normally two types of shaft gland seals are in use in different power stations:

i) Carbon or ferrobestos segment.

ii) Rubber flap type

 4.3.1 Carbon or Ferrobestos Segment Type

 The seal segments are housed in the stuffing box. Stuffing box being always in touch with the shaft is subjected to excessive wear and tear. The overhauling of the stuffing box becomes necessary when it is observed that consumption of cooling water has considerably increased or excessive water in top cover appears to be coming. In general maintenance of the seal is required to be done annually.

In the event of breakage or damage to a carbon segment it is advisable to replace the whole set of carbon segments. In very rare case only the damaged segment is replaced care must be taken to ensure that the axial thickness of the new segments falls within the limit size to ± 0.002” of the existing ring to which it is to be fitted.

All carbon segments and spacers are fitted to place and match marked on assembly. Whenever any part is replaced, matching marks / indents should be made after final assembly is satisfactorily completed. Whenever reassembly of the gland seal with existing gland ring or new ring is done it is important to ensure:

1. All carbon/ ferrobestos segments are carefully examined for any chipping or damage.

2. All stainless steel facings are flat and square with the gland sleeve and there are not steps at the facing joints.

3. Stainless steel facing and sleeve are completely free from grease.

4. Ensure proper bedding of segments with shaft sleeve.

5. All segments to segment and segment to stainless steel mating surface are completely free from grease.

6. All garter springs are assembled to obtain even tension all around.

7. Alignment of segments in the lower assembly is carefully checked with a hard wood peg for similar device before fitting retaining pins.

 4.3.2 Rubber flap type

Maintenance of rubber flap type gland seal is comparatively simpler and easier. Only precaution during assembly of rubber gland is jointing of the rubber seal in the proper way. The quality of rubber used plays a very important role for satisfactory performance of the rubber gland. In one of the recently commissioned power stations rubber gland seal used to fail very frequently. The cause of frequent failure was discussed and analysed to be lying in the quality of rubber. The problem after selection and use of proper quality of rubber is now over.

4.4 Guide vane servomotor

Normally main source of trouble is rubber seals which need to be replaced after a few years. Rubber seals should be replaced during annual maintenance. It is important that all the parts are match marked before dismantling so that reassembly is correctly done.

 4.5 Governor

Different types of governors are in use in different hydro power stations:

a) Mechanical governor can be classified as follows

i) Fly ball type

ii) Accelero technometric type

b) Governor employing magnetic amplifier.

c) Governor employing electro hydraulic amplifier.

The governor may require maintenance because of the following reasons:

i) Chocking of oil parts and throttles

ii) Wearing out of throttles due to which oil leakage becomes more and readjustment of governor becomes essential. In this case governor should be opened and all the throttles etc. should be cleared. Filters should also be cleaned, and after cleaning and reassembly governor parameters and characteristics should be readjusted so that there is no hunting of the governor.

4.6 Governing Oil System

The oil sump should be well cleaned and filled with filtered oil. The oil samples should be got tested for verification of the desired properties. Regular centrifuging of oil with the help of De-Laval type oil purifying machine would go a long way in enhancing the life of the oil. In certain cases oil retained its properties even up to 15 to 20 years of continuous use.

During annual overhauling OPU sump and pressure accumulator should be completely emptied and cleaned. The strainers should be inspected and repaired of necessary. The OPU pumps require maintenance when they develop excessive noise or vibrations. This may be due to some worn out bearing of the pump which would be replaced.

Another problem which has been faced in different power station is entry of water in the governing oil system. This problem was analysed in detail and remedial measures were taken at Chila Power Station. From following two sources the water can enter in the governing oil system:

1. From top cover, through oil leakage pumps which caters leakage of servo motor oil. Its sump being located well below the level of servo motors in the top cover may not be properly sealed, thus providing access to the top cover water which may ultimately be pumped in to the OPU sump.

2. In case of Kaplan turbine water may enter into the runner hub through cup seals. To eliminate first possibility the oil leakage unit delivery was isolated from the OPU sump and connected to a separate tank.

But for the second possibility there is no way except replacing blade seals if excessive water found in the Governor oil.  Daily check of the OPU sump oil sample and test of the sample is necessary to keep training of such possibilities.

4.7 Header

 In Kaplan turbine the oil header is required to supply governing oil to the runner servomotor and return oil to the OPU sump. Oil header has an oil guide connected with the rotating and servo tube. The servo tube has ports to receive return oil to the pipes coming from OPU sump. This tube is guided by three sets of bushes in the oil. Due to run out of the shaft these bushes had to press the servo tube. Failure of these had been very frequent in one of the recently commissioned power station.

Monitoring of wobbling of the servo tube with help of dial indicator may provide a guide line and save the bushes from further wearing. Remedial measures to reduce run out of the servo tube must be taken at this stage.

At the time of assembly of various parts of header proper match marking and dowelling is essential so that reassembly may be correctly done.

Due to failure of these bushes oil splashing occur which may drench the PMG, main & Pilot exciter and reduce the life expectancy of the windings and brush as such all out efforts should be made to prevent such happenings.

Operation and maintenance of hydropower stations planning and management – an Indian perspective-Part 3

Posted on April 20th, 2012 by admin  |  No Comments »

Turbine Auxiliaries

1. DPM

i) Inspect top cover drain system, overhaul the ejector and drainage pumps.

ii) Check pipe lines and valves. Replace gaskets and other parts, if necessary.

2. Oil Cooling Unit

i) Overhaul cooling pumps

ii) Attend all the valves and pipe lines for leakage.

3. Centralized Grease Lubrication System

i) Overhaul greasing pumps

ii) Check whole greasing lines. Replace worn out valves and gaskets etc.

iii) Check all the nylon pipes connected with the guide vane bushes. Replace damaged pipes.

iv) Check that all the guide vanes are receiving grease properly.

4. Oil Leakage Unit

i) Check the oil leakage unit overhaul the pumps.

ii) Clean tank and check that float is properly working.

iii) Checking all the pipe liens and valves for leakages.

 3 Requirement of effective maintenance

In addition to planning maintenance and implementing a suitable schedule (on the basis of seasonal water availability perhaps), the following items also require attention otherwise it may be difficult to keep to the schedules in practice:

1. Man Power Planning and arrangement is essential as without experienced and skilled staff any maintenance programme may fall.

2. Planning and arrangement of spares and consumable in advance so that time is not lost in re-commissioning the plant after the shut down.

3. The maintenance engineers should have in his possession all the erection and commissioning log sheets documents to establish a record of installed learances, parameters, alignment results, test characteristics of all the power plant equipment. These may be required at the time of diagnosis of the operational problems as well as defined maintenance purpose.

4. Log sheets of the previous maintenance exercise carried out on the machines. These may be required to compare with the clearances / settings / characteristics achieved during present maintenance.

5. History registers of all plant should be kept with records of all the abnormalities observed on the machine and details of action taken. This data can be used to as a guideline for future maintenance work at the power station.

6. Logging of the performance characteristics of the power plants on daily basis recording all the abnormalities and misbehaviours (if any) of the total plant observed during its generation programme from one maintenance exercise to another.

 4 Major maintenance problems of water turbines

 Some of the major problems encountered in the hydro turbines are damage in runners due to erosion, cracking and cavitation due pressure pulsation in draft tube, instability of operation at partial gate opening. Other serious issues include failure of turbine guide bearings, leakages of water through turbine guide bearings, leakage of water through guide vane seals and turbine gland seals. These problems are discussed in detailed in the following section.
 4.1 Runner

 4.1.1 Erosion due to silt

Erosion of turbine runners, guide vanes and other under water parts is a serious service problem especially in run-of-river schemes. The rivers in the Northern region of India carry significant silt loads especially during monsoon period so much so that hydro power stations are often closed down to prevent serious damage to the turbines parts and water passage.

Greater attention should, therefore, be paid to effective de-silting arrangements. Excessive wear and damage often occurs on the runner labyrinths, seals, guide vanes, butterfly valves, shaft seals and draft tube cone. Wear due to silt occurs so fast that the turbine units have to be taken out for repair every few months in some stations. The solution lies in the original specification of effective de-silting civil works however, this is of little practical help in the service environment. In the service environment the use of turbine parts coated with or made from material with harder and erosion resistant properties is the most practical option to be pursued.

At Chilla Project following measures of de-silting have been taken:

i) Silt extruders have been provided near under sluice gates of the barrage.

ii) Half a kilometre downstream of the head regulator, a silt ejector has been constructed in the bed of the power channel.

 4.1.2 Cavitation related cracking and wear of the runner

The problem of cracks in turbine rotors and Pelton buckets has been reported in few power stations. This can be due to following reasons.

i) Faulty design

ii) Poor metallurgy

iii) Metal fatigue

The phenomenon of cavitation occurs due to the vaporization of water in a zone of excessive low pressure. Cavitation damage can occur if the turbine has to operate at part flow. Limits of structural wear (metal removal) are normally specified beyond which repair of the plant is needed. To minimize the effects of cavitation, the following steps are recommended:

i) Periodically (annual) inspection of the runner and other turbine parts to judge when repair is necessary.

ii) Operation of the turbine plant according to the manufacturers guidelines. Specifically, a turbine unit should not be run below the minimum load (discharge), recommended by the manufacturer.

iii) At design stage, ensure i) proper submergence of the turbine ii) correct specifications of cavitation resistant materials and

iii) specification of the runner profile based on model tests for cavitation onset.

iv) As a result of draft tube pulsation and surges at no load or part gate opening excessive noise, vibrations and cavitation is experienced. To minimise pulsations of draft tube following measures must be taken:

- Air admission through air admission/ vacuum breaking valve installed at top cover.

-Provision of fins or flow splitter in draft tube to break the vortex flow.

- Provision of a bypass arrangement for releasing the pressure built up below the top cover.

Normally the discharge side surface of buckets or blades, areas on the crown on the throat ring and the tip of the blades and the upper portion of the draft tube liner are affected by the action of cavitation. In rare cases, there may be pitting on the pressure faces of the buckets or blades due to an unusual amount of over hung of the guide vanes improper design or unusual operating conditions.

Hydro Power plant operators have, over the years, gained expertise of ways of repairing and welding of the runner at site, but it becomes a regular maintenance problem as wear and cracking occurs quickly.

4.1.3 Precaution in welding of runners

 Some general remarks about the welding repair of turbine runners are given below. It should be noted that different materials will require specific (often proprietary) welding processing.

1. Surface of the parent material should be prepared by chipping or grinding.

2. To locate cracks, inclusions and the like, a die penetration test must be carried.

3. Preheating of the blade to about 60oC is necessary

4. Avoid any localized excessive heating. This is achieved by welding for a short time in any one particular area and then moving to a diametrically opposite area to continue with the work.

5. The parent material should be about 70 to 75 mm from the weld and should not be allowed to get too hot to be touched with bare hand.

6. Plenty of time should be allowed for the welded area to cool down since forced cooling may cause distortion due to locked in stresses. Hot peening is also required.

7. A close check should be made at least two to three times per day during the repair for runner to runner chamber clearances.

8. After welding all the welded areas should be properly ground to match with the desired profiled.

9. Die penetration tests should once again be carried out to ensure crack free welding.

Rectification if necessary should be done.

If extensive welding on the runner is required, it will be necessary re-balance statically and possibly dynamically all rotating parts and stress relieving before recommissioning otherwise.

Operation and maintenance of hydropower stations planning and management – an Indian perspective Part-II

Posted on April 20th, 2012 by admin  |  No Comments »

2.1.2. Weekly Maintenance Checks:

 1. Greasing of guide vanes and servomotor with centralized grease lubrication system and manually.

i)  Oil in the gear box shall be checked.

ii)  Check for any leakage

iii) Working of end pressure relay and solenoid valves, if defective, should be reported.

2. Cleaning of OPU filters

3. Cleaning of throttle filters in the governor mechanical cabinet.

4. Cleaning of governor compressor air filters and checking of oil levels.

5. Checking physically oil of OPU of the running machine after sample taking through the sampling cock and do the crackle test for detecting presence of water. Take remedial measures.

6. Check oil level of all the bearings.

Check wobbling of shaft at coupling flange and at oil header servo-tube.

2.1.3. Monthly Maintenance Checks

 All the checks covered as part of the weekly maintenance are also carried out as part of the monthly check. In addition to these checks, more attention is paid and short shutdowns, if required, for rectification are taken.

2.1.4. Annual Preventive maintenance of Hydro Turbines

 After successful running of plant for about one year, a few weeks are required to inspect rotating parts, control equipment and measuring instruments and to analyze the cause of changes in the performance characteristics, if any. Modify, repair or replace (wherever required) worn out parts in order to prevent unplanned outages of plant at later date.

After every five years it is necessary to inspect the machine more critically for abnormalities like fatigue defects or excessive wear and tear of some parts or any change in original parameters/clearances etc. This exercise becomes very essential in cases where performance level has been observed to have gone down in 5 years operation.

The checks for annual and five yearly maintenance specified for Chilla Power Station are enlisted below:

1. Foundation Parts:

i) Check condition of water path system. The damage due to cavitation and wear to be rectified.

ii) Check painting of spiral casing.

2. Runner:

Check the condition of the surfaces of the runner hub and the blades. The damage due to cavitations & wear to be rectified by welding and grinding.

ii) Check the runner blade seals by pressurizing the system. Change seals if necessary. No oil leakage is to be allowed.

iii) Check the runner sealing for hermetic tightness, leakages of water in the runner hub is not to be permitted.

3. Guide Apparatus:

i) Check the presence of rubber sealing cords and the tightness of the rubber sealing between the adjacent guide vanes in fully dosed position of guide apparatus.

ii) Change oil in the regulating ring.

iii) Replace damaged shear pins.

iv) Check cup sealing of guide vane journals and replace, if necessary.

v) Check the bushes of guide vanes and change the worn out bushes of guide vanes journals.

vi) Inspect the servomotor and change the seals, if these are worn out.

4. Guide Bearing:

i) Check the condition of rubbing surfaces of guide bearing. Clean the surface and polish it with the help of chalk powder.

ii) Adjust the clearances by moving the segments with the help of adjusting bolts.

iii) Thorough cleaning of housing if necessary.

iv) Check all the RTDs and TSDs replace damaged one.

5. Shaft Gland Seal and Air Seal:

i) Check the condition of rubbing surface of sealing rings. In case found damaged change the same.

ii) Check pipe lines and piping joints for any leakage if any, attend the same.

6. Emergency Slide Valve:

i) Check the functioning of emergency slide valve and the condition of inner surfaces.

ii) Swift return of the valve in its original position after emergency operation should also be checked.

7. Centralised Grease Lubrication System:

i) Check satisfactory working of CGLS system.

ii) Attend wherever fault is located.

8. OPU:

i) Check and attend leakage from any valve or flanged joints etc.

ii) Provide proper lubrication to the bearings of pump motor.

iii) Check filter and repair, if required.

iv) Clean oil sump, refill with centrifuged oil.

v) Check setting of the float relays for proper sequence of operation of pumps.

9. Oil Header:

i) Measure clearances of upper and lower bushes, if found increased get the bushes replaced.

ii) Clean the oil bath.

iii) Check the rubber cord fixed below the guide to check any oil dipping on the exciter winding.

10. Oil Leakage Unit:

i) Check satisfactory working on Auto as well as manual.

ii) Clean the tank.

iii) Check the pipeline joints and valves for leakage, attend wherever necessary.

11. Oil Cooling Unit:

i) Check all the oil and water pipe lines for leakage and attend if necessary.

ii) Check satisfactory working of all cooling unit.

12. Governor Mechanical Cabinet:

i) Check filter and throttle if found damaged replace the same.

ii) Attend leakage of oil through pipe line joints and valves.

iii) Check auto rod setting, if found disturbed; set the same.

iv) Check (Alpha – Beta) characteristic, if found disturbed set the same.

Alignment of feed back wire rope pulleys.

 2.1.5. Capital Maintenance

Overhauling or capital maintenance of hydro plant is usually recommended after about 10 years of operation services. The whole unit is to be stripped off during capital maintenance and all the defective/worn out parts/components repaired/replaced with new ones. Then the unit is re-commissioned as per originally established commissioning practice of the power station.

After capital maintenance the units are subjected to all maintenance exercise outlined above before it reach the next cycle of capital maintenance.

Following checks are to be exercised during capital maintenance of a hydro set:

1. Turbine Bearing:

i) Dismantling, inspection, cleaning, measurement of clearances, polishing of guide pads, centering of shaft, reassembly, setting of clearances, filling of oil sump with filtered water.

ii) Check the temperature sensing device, if necessary, replace with new ones.

2. Gland Seals and Isolating Air Inflated Seals:

Dismantling, inspection, cleaning and reassembly. Replacing of worn out rubber flaps or carbon segments, if necessary.

3. Clean Water System:

Clean water pipes are dismantled, cleaned, reassembled with new gasket all the valves are attended for any leakage etc.

4. Guide Vane Servomotor:

Dismantling for inspection and cleaning. Reassembling and replacing the seals with new ones, if necessary.

5. Guide Vanes Bush Housing:

i) Removing, cleaning and inspecting for wear and tear replacing with new ones if found necessary. Replace seals, if necessary.

ii) Guide vanes are reconditioned.

6. Governor:

i) Cleaning and checking OPU pumps. Replace bushes, bearings etc. if found worn out. Also attend pump motors.

ii) Cleaning OPU sump and pressure accumulator and refill with filtered oil.

iii) Attend oil pipeline flanges and valves for leakages.

iv) Check setting of pressure switches installed for Auto Operation for OPU pumps.

v) Attend Governor Mechanical cabinet for leakages, loose links. Clean main and pilot slide valves. Set Auto rod as per designs Alpha Beta setting may also be checked.

vi) Check electrical circuit. Tightening of all the connections should be done.

7. Submerged Parts

i) Cleaning and painting of spiral casing and draft tube liner.

ii) Overhauling of spiral drain valve and draft tube drain valve.

8. Runner

i) De-watering of draft tube and fabrication of platform in the draft tube for inspection of runner.

ii) If it is a Kaplan Runner test the same after applying full governor pressure for leakage of oil.

iii) Replace blade seals, if necessary.

iv) Inspect blades of the runner and make up profile of the blades by welding. Due to erosion, abrasion and cavitations, material of the blade washes away with passage of time.

v) In case the runner is found to be irreparable arrange to replace the same with new one.

Operation and maintenance of hydropower stations planning and management – an Indian perspective

Posted on April 14th, 2012 by admin  |  No Comments »

Experience of running hydro power stations in India has shown that even after careful project planning and good quality control measures from construction to commissioning, unforeseen problems do occur in service resulting in unplanned outages / low generation and load shedding etc. This causes disruption to consumers and reduced cash generation for the operator. A contributing factor to these operational problems is the fact that hydro power equipment and plant is custom built. The equipment cannot be fully assembled or tested in a factory before sending it to site. Maintenance activities at predetermined time intervals are necessary to ensure the following:

1. Quality and reliable operation of equipment in the service environment through planned, periodic inspection and checking of components and systems. Together with replacement or rectification of parts wherever required.

2. Maximum availability of equipment and a minimum of unplanned shut downs by using planned / periodic shutdowns to inspect all equipment (serviceable and non-servicable).

3. Eradication of operational problems by a timely analysis of the cause of faults / problems and replacement of short term solutions by long lasting and permanent ones.

2 Preventive maintenance of Hydro turbine

In order to achieve above objectives of maintenance, time has to be allotted every year for each machine. Normally the periodicity and the procedure for maintenance is recommended by the manufacturer of the equipment. However, experience of operators of Hydro Power Stations in India has shown that the maintenance is required according to the following guidelines.

Routine Maintenance

Normally there will be daily, weekly, monthly and quarterly checks as per the maintenance schedules are done. These checks are necessary for controlling any change in the installed clearances, commissioning characteristics etc. connected with the performance of equipment. Rectification and adjustment wherever required should be carried out in order to arrest any deterioration of the equipment. The daily, weekly and monthly check schedules designed for Chilla Hydro Power Station are used to illustrate the kind of maintenance schedule that will be needed:

2.1.1. Daily Maintenance Checks

 1. Foundation Parts and Expansion Joints:

Check for any leakage in draft tube manholes, spiral casing manhole, expansion joint.

2. Vacuum Breaking Valve:

Check the working of both vacuum breaking valve and see that there is no abnormality in the springs, seats etc.

3. Water Seal and Air Seal:

  • Check the position of water leakage around the water seal and check that there is no
  • excessive splashing and water level do not rise in top cover.
  • Note water pressure of water sealing/under sealing.
  •  4. Turbine Guide Bearing:
  •  Check the oil level (stand still machine/running machine).
  •  Note the temperature of bearing and check that the temperature of oil and guide bearing pads are within limits.
  •  Note the maximum and minimum temperature of the previous day.
  •  Check for any oil leakage from the bearing housing and check that oil is flowing above the bearing pads.

5. Guide Apparatus:

Check any leakage from GV servomotor and its piping.

Oil Leakage Unit:

  • Check any leakage from pipe line joints.
  • Check its satisfactory running on `Auto’.

Top Cover Drain System:

  •  Main supply of `ON’ for DPM.
  • Vibration noise in the pump motor.
  • Any leakage from the water piping.
  • Working and water pressure of the ejector.

Centralised Grease Lubrication System:

  •  Check for any leakage from grease pipes, unions and nipples.
  •  Check grease container and fill grease, if required.

Oil Header:

  • Check from perspex sheet manhole any splashing of oil from top and bottom bush.
  •  Check any oil leakage from the joints.
  •  Note the pressure difference of opening and closing side of runner.

Oil Pressure System:

  • Check if there is any abnormal sound in the running of the motor and pump unit of OPU.
  •  Check the oil level in pressure accumulator.
  • Check any oil leakage from oil piping and its valve.
  • Check for over heating of motor.
  •  Note the timing of OPU pumps running.

Mechanical Cabinet of Governor:

  • Pressure in transducer.
  • Check any oil leakage from joints of piping.
 
Google plus one provided by best online casino sites